Practical completion and handover on a renovation

How to close out a renovation: what practical completion means, the final walk with the client, agreeing extras, signing off fixes and what to hand over.

Handover is where a renovation job is won or lost. The work can be good, but if the last few weeks are messy, with snags dragging on, extras in dispute and paperwork missing, that is what the client remembers. This guide covers how to close out a job cleanly. It is general guidance, not legal advice. The terms that apply to you are in your contract, so check it.

01What practical completion means

Practical completion is the point at which the work is finished enough for the client to use the property as intended. It does not mean perfect. There may still be minor snags, as long as they don’t stop the client using the space and it is agreed they will be put right.

A lot can hang on it. Depending on your contract, practical completion may be when the client takes over insuring the property, when the defects period starts, when part of any retention is released and when the final account is settled.

Some contracts define it carefully. Many small renovation contracts don’t mention it at all. Read yours, and agree with the client what “finished” means before you get there.

02Before the final walk

  • Do your own snag walk first, without the client, and get the trades back to fix what you find.
  • Check every fix yourself. Don’t rely on a trade saying it is done.
  • Get the clean done properly. Dust on top of door frames and inside cupboards gets noticed.
  • Pull together the paperwork you need to hand over, so you are not chasing certificates afterwards.
  • List the extras and where each one stands, so you know what has been approved and what hasn’t.

03The final walk with the client

Walk the job with the client room by room. Let them point things out, and note each one while you are standing there. Don’t argue each item on the spot. Agree that it goes on the list, and decide afterwards whether it is a snag you will fix, an extra, or something that was never part of the job.

If you are recording the walk, tell the client at the start. Take a photo of anything they raise. When you send the list afterwards, it should match what they remember saying.

At the end of the walk, agree what has to be done before the client moves in and what can be done after. Write that down too.

04Agree extras in writing before handover

Extras often cause more trouble at the end of a job than snags do. The client asked for something on site, a trade did it, and now nobody agrees whether it was included or what it costs.

The answer is to agree every extra in writing before the work is done: what it is, the price and any effect on the programme. If some extras slipped through without that, sort them out before handover, not in the final invoice. A client who has already signed for an extra is far less likely to dispute it later.

05Signing off fixes

Every snag needs a clear end. For each one, check the fix against what you asked for, ideally with a before and after photo of the same spot. Then either sign it off or send it back with a short note on what is still wrong.

Keep the record. It shows the client what was done, and protects you if the same issue comes up again.

06What to hand over

Put everything in one place, as a folder, a file or both, and walk the client through it.

  • Certificates. Electrical, gas and building control sign-off, and any others that apply to the work you did.
  • Warranties and guarantees. For the boiler, appliances, windows, doors, worktops and any other products that come with one. Register them if the manufacturer asks for that.
  • Manuals. For the boiler, heating controls, extractors, appliances and anything with settings the client will need.
  • Keys. For every door, window and lock, labelled. Include any codes for alarms or key safes.
  • Where things are. The stopcock, isolation valves, consumer unit and any access panels.
  • Product details. Paint colours and finishes, tile names and any spare tiles, so later repairs can match.
  • The snag list. What was found, what was fixed and when it was signed off.

07The defects period and retention

Many contracts include a defects period after practical completion. During it, the builder puts right defects that appear, such as cracks as the building dries out, joints that weep or doors that drop. Some contracts also let the client hold back a retention, a small part of the contract sum, until the end of that period.

How long the period lasts, how defects are reported and when any retention is released all depend on your contract. Check it, and explain it to the client at handover. Book a walk at the end of the period, so you can deal with everything in one visit and close the job properly.

08Keeping it all in one place

Snagwalk keeps the end of a job together. Walk with the client and talk as you go, and it turns the recording into snags for each trade, extras for you to price, and the things you signed off. The client gets a link to approve the extras and sign on their phone, and you both get a signed copy.

Trades mark fixes with a photo, you compare before and after, and you sign each one off or send it back. The job report PDF gives you a record of the lot to keep with the handover pack.

Your next walk, sorted.

Snagwalk is on Google Play now. The App Store version is on its way.

Get it onGoogle PlayApp StoreComing soon